Installation:

"Y" strainers should be installed in a horizontal line or a vertical line with the flow going down.

Basket strainers should be installed in a horizontal line. In both styles room must be allowed for screen removal.

Ideally, pressure gauges should be installed upstream and downstream of a strainer to indicate pressure drop caused by a partially plugged screen.

Maintenance:

Determine how long it takes for the screen to become approximately 1/3 plugged and remove and clean at the same time interval, or when the pressure gauges, if installed, indicate a pressure drop across the strainer.

If a "Y" strainer has been provided with a blow-down valve on the drain connection then it may be opened to blow down sediment.

Spare Parts:

A spare screen and cover gasket are the only parts required to refurbish a strainer.

A spare screen will decrease shut-down time while the plugged screen is being cleaned.
 

 
 